QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Thermo Fisher Inchinnan Solar Generator Alternative Feed

At Erskine

SPEN Embedded Capacity Register >1MW, April 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2029
Status
Accepted to connect
Customer
Not stated
Site name
Thermo Fisher Inchinnan Solar Generator Alternative Feed
Address
Not stated
Grid reference
Easting 245710, northing 667721
Licence area
Central and Southern Scotland (SPD)
Grid supply point
Erskine
Bulk supply point
Not stated
Primary substation
ERSKINE (11kV)
Connection voltage
11 kV
Technology group
Solar
Energy source 1
Solar, Photovoltaic: 3.132 MW registered
Registered capacity
3.132 MW
Change to maximum export capacity
0 MW
Change to maximum import capacity
0 MW
Flexible connection
No
In a connection queue
Yes
Date accepted
Not stated
Date connected
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
22 Apr 2026
Tracked since
April 2026 edition

Change history

Found in the April 2026 edition only.

Another record at this location is on a separate page.

Changes to its status, capacity, technology or customer, newest first.

  • May 2026 edition
    Not found in this edition by its MPAN, grid reference or name and postcode

No changes to show: it has been found in one edition.

Also at Erskine

GSP view

8 other sites at this grid supply point in the September 2026 edition, 4 of them at ERSKINE (11kV), the same primary substation. In all, the sites here total 151 MW: 108 MW connected, 43 MW accepted to connect.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose