THE ENERGY CENTRE BUILDING
SSE HEAT NETWORKS LIMITED at THAMESMERE
SSEN Embedded Capacity Register, April 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Date connected
- Not stated
- Status
- Connected
- Customer
- SSE HEAT NETWORKS LIMITED
- Site name
- THE ENERGY CENTRE BUILDING
- Address
- THE WARREN, LONDON, GREATER LONDON, SE18 6TF
- Grid reference
- Easting 544012, northing 179211
- Licence area
- Southern England (SEPD)
- Grid supply point
- THAMESMERE
- Bulk supply point
- THAMESMERE
- Primary substation
- THAMESMERE
- Connection voltage
- 11 kV
- Technology group
- Other or not stated
- Energy source 1
- 1.14 MW registered
- Registered capacity
- 1.14 MW
- Maximum export capacity
- 1.14 MW
- Maximum import capacity
- Not stated
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- Not stated
- Target energisation date
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- 2000054264883
- Import MPAN
- 2000054264874
- Last updated
- 10 Feb 2026
- Tracked since
- October 2025 edition
Change history
Tracked from the October 2025 edition to the April 2026 edition, across 7 editions.
Changes to its status, capacity, technology or customer, newest first.
- May 2026 editionNot found in this edition by its MPAN, grid reference or name and postcode
No change to its status, capacity, technology or customer.
Also at THAMESMERE
GSP viewNo other site in SSEN's September 2026 edition is at this grid supply point.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose