CLAYFORDS ENERGY STORAGE
INTELLIGENT LAND INVESTMENTS GROUP PLC at STRICHEN
SSEN Embedded Capacity Register, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Oct 2033
- Status
- Accepted to connect
- Customer
- INTELLIGENT LAND INVESTMENTS GROUP PLC
- Site name
- CLAYFORDS ENERGY STORAGE
- Address
- CLAYFORDS ENERGY STORAGE, CLAYFORDS FARM STRICHEN, FRASERBURGH, ABERDEENSHIRE, AB43 6RH
- Grid reference
- Easting 396561, northing 854772
- Licence area
- North of Scotland (SHEPD)
- Grid supply point
- STRICHEN
- Bulk supply point
- Not stated
- Primary substation
- STRICHEN GRID
- Connection voltage
- 33 kV
- Technology group
- Storage
- Energy source 1
- STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 49.9 MW registered
- Registered capacity
- 49.9 MW
- Change to maximum export capacity
- 49.9 MW
- Change to maximum import capacity
- 52.526 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 8 Nov 2021
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 10 Feb 2026
- Tracked since
- December 2025 edition
Change history
Tracked since the December 2025 edition, across 10 editions.
Changes to its status, capacity, technology or customer, newest first.
No change to its status, capacity, technology or customer.
Also at STRICHEN
GSP view14 other sites at this grid supply point in the September 2026 edition, 11 of them at STRICHEN GRID, the same primary substation. In all, the sites here total 215 MW: 20 MW connected, 195 MW accepted to connect.
- STRICHEN NORTH ENERGY PLANTTHE GRID CONSULTANT, Other or not stated, STRICHEN GRID primaryAccepted25 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose