SEMBCORP UTILITIES (UK) LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Wilton CCGT Project 1 | Greystones B 275kV Substation | Thermal (gas, biomass, waste) | 850 | 30 Oct 2035 | Not stated | Consents Approved |
| Wilton CCGT Project 2 | Greystones A 275kV Substation | Thermal (gas, biomass, waste) | 700 | 30 Oct 2035 | Not stated | Consents Approved |
| Wilton | Wilton 66kV Substation | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Wilton CCGT Project 1England and Wales, Thermal (gas, biomass, waste)Status changed from Scoping to Consents Approved
- Wilton CCGT Project 2England and Wales, Thermal (gas, biomass, waste)Status changed from Scoping to Consents Approved
- Wilton CCGT Project 1England and Wales, Thermal (gas, biomass, waste)Added to the registerNew
- Wilton CCGT Project 2England and Wales, Thermal (gas, biomass, waste)Added to the registerNew
- WiltonEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Greystones A 275kV Substation to Wilton 66kV Substation
- WiltonEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from DNO - Wilton 66kV to Greystones A 275kV Substation
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?