SAGE NORTH SEA LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| SAGE | St Fergus Mobil 132/11kV Substation | Solar | 20 | 30 Apr 2029 +46 mo | Gate 1 | Scoping |
Recent changes
- SAGENorth Scotland, SolarConnection date moved from 30 Jun 2025 to 30 Apr 2029 (+46 months)+46 mo
- SAGENorth Scotland, SolarSubstation name updated in the register (from St Fergus Mobil to St Fergus Mobil 132/11kV Substation)
- SAGENorth Scotland, SolarMarked as Gate 1
- SAGENorth Scotland, SolarRenamed from SAGE Solar
- SAGENorth Scotland, SolarConnection point changed from REVIEW - St Fergus Mobil to St Fergus Mobil
- SAGENorth Scotland, SolarConnection point changed from St Fergus Mobil to REVIEW - St Fergus Mobil
- SAGENorth Scotland, SolarCustomer changed from Ancala Midstream Acquisitions Limited to SAGE NORTH SEA LIMITED
- SAGENorth Scotland, SolarAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?