RPC ELMYA CARNATION KILWORTH LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Elmya Kilworth BESS & PV | Derbyshire Connection Node H 400kV Substation | Storage with solar or wind | 850 | 30 Oct 2037 | Gate 1 | Scoping |
Recent changes
- Elmya Kilworth BESS & PVEngland and Wales, Storage with solar or windAdded to the registerNew
- Elmya Kilworth BESS & PVEngland and Wales, Storage with solar or windLeft the register (850 MW from 30 Oct 2037)850 MW
- Elmya Kilworth BESS & PVEngland and Wales, Storage with solar or windMarked as Gate 1
- Elmya Kilworth BESS & PVEngland and Wales, Storage with solar or windCustomer changed from RPC ELMYA CARNATION DEVCO LIMITED to RPC ELMYA CARNATION KILWORTH LIMITED
- Elmya Kilworth BESS & PVEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?