Rosefield Energyfarm Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Rosefield | East Claydon 400kV Substation | Storage with solar or wind | 500 | 31 Oct 2031 | Not stated | Awaiting Consents |
Recent changes
- RosefieldEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2028 to 31 Oct 2031 (+36 months)+36 mo
- RosefieldEngland and Wales, Storage with solar or windRenamed from East Claydon
- RosefieldEngland and Wales, Storage with solar or windCustomer changed from CUSTODIAN ENERGY LIMITED to Rosefield Energyfarm Limited
- RosefieldEngland and Wales, Storage with solar or windConnection point changed from East Claydon 400V Substation to East Claydon 400kV Substation
- RosefieldEngland and Wales, Storage with solar or windConnection date moved from 30 Nov 2025 to 30 Oct 2028 (+35 months)+35 mo
- RosefieldEngland and Wales, Storage with solar or windConnection point changed from East Claydon to East Claydon 400V Substation
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?