RICHBOROUGH ENERGY PARK LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Richborough 1 | Richborough 400kV Substation | Storage | 0 | Connected | Not stated | Built |
| Richborough 2 | Richborough 400kV Substation | Storage | 0 | Connected | Not stated | Built |
Recent changes
- Richborough 1England and Wales, StorageCapacity changed from 50 MW to 0 MW
- Richborough 2England and Wales, StorageCapacity changed from 50 MW to 0 MW
- Richborough 1England and Wales, Storage50 MW now connectedConnected
- Richborough 1England and Wales, StorageCapacity changed from 50 MW to 100 MW
- Richborough 2England and Wales, Storage50 MW now connectedConnected
- Richborough 2England and Wales, StorageCapacity changed from 50 MW to 100 MW
- Richborough 1England and Wales, StorageConnection date removed (was 24 Nov 2023)
- Richborough 1England and Wales, StorageStatus changed from Scoping to Built
- Richborough 2England and Wales, StorageConnection date removed (was 25 Aug 2023)
- Richborough 2England and Wales, StorageStatus changed from Scoping to Built
- Richborough 1England and Wales, StorageConnection date moved from 28 Apr 2023 to 24 Nov 2023 (+7 months)+7 mo
- Richborough 2England and Wales, StorageConnection date moved from 30 Jun 2023 to 25 Aug 2023 (+2 months)+2 mo
- Richborough 1England and Wales, StorageSubstation name updated in the register (from Richborough to Richborough 400kV Substation)
- Richborough 2England and Wales, StorageSubstation name updated in the register (from Richborough to Richborough 400kV Substation)
- Richborough 1England and Wales, StorageConnection date moved from 30 Jun 2022 to 28 Apr 2023 (+10 months)+10 mo
- Richborough 2England and Wales, StorageConnection date moved from 31 Oct 2022 to 30 Jun 2023 (+8 months)+8 mo
- Richborough 1England and Wales, StorageSubstation name updated in the register (from Richborough 400kV to Richborough)
- Richborough 2England and Wales, StorageSubstation name updated in the register (from Richborough 400kV to Richborough)
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?