Projects / Company
NEW ENERGY PARTNERSHIP LIMITED
Customer named in the TEC register
4projects in the register
462 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| 012 NEP Coventry West | Berkswell GSP | Storage | 92.4 | 31 Oct 2034 | Not stated | Scoping |
| 014 NEP Bransholme | North Humber Connection Node C 132kV Substation | Storage | 40 | 30 Oct 2035 | Not stated | Scoping |
| Coylton Farm | Coylton 275/33kV Substation | Storage | 300 | 30 Oct 2037 | Not stated | Awaiting consent |
| Barrow | Harker 132kV Substation | Storage | 30 | 31 Oct 2037 | Not stated | Scoping |
Recent changes
No changes here since 14 Aug 2026.
QueueQuant
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose