NANT MITHIL ENERGY PARK LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Nant Mithil Energy Park | Pont Abraham 132KV | Onshore wind | 253 | 31 Oct 2026 Past date | Not stated | Scoping |
Recent changes
- Nant Mithil Energy ParkEngland and Wales, Onshore windRenamed from Fron Goch
- Nant Mithil Energy ParkEngland and Wales, Onshore windConnection point changed from Pont Abraham GSP to Pont Abraham 132KV
- Nant Mithil Energy ParkEngland and Wales, Onshore windSubstation name updated in the register (from Pont Abraham to Pont Abraham GSP)
- Nant Mithil Energy ParkEngland and Wales, Onshore windAgreement type changed from Directly Connected to Embedded
- Nant Mithil Energy ParkEngland and Wales, Onshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?