GALILEO 01 LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Hunterston Wind Farm | Hunterston 400/132kV | Storage with solar or wind | 70 | 30 Apr 2033 | Gate 1 | Scoping |
Recent changes
- Hunterston Wind FarmSouth Scotland, Storage with solar or windMarked as Gate 1
- Hunterston Wind FarmSouth Scotland, Storage with solar or windConnection date moved from 30 Aug 2030 to 30 Apr 2033 (+32 months)+32 mo
- Hunterston Wind FarmSouth Scotland, Storage with solar or windConnection point changed from Hunterston Farm 132/33kV to Hunterston 400/132kV
- Hunterston Wind FarmSouth Scotland, Storage with solar or windTechnology changed from Onshore wind to Storage, Onshore wind
- Hunterston Wind FarmSouth Scotland, Storage with solar or windSubstation name updated in the register (from Hunterston Farm GSP to Hunterston Farm 132/33kV)
- Hunterston Wind FarmSouth Scotland, Storage with solar or windCustomer changed from Galileo Empower UK Limited to GALILEO 01 LIMITED
- Hunterston Wind FarmSouth Scotland, Storage with solar or windCustomer changed from GGE SCOTLAND LIMITED to Galileo Empower UK Limited
- Hunterston Wind FarmSouth Scotland, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?