EKU ENERGY FAUNE PROJECTS (UK) LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Drumfad Battery Storage System | Helensburgh 132/33kV | Storage | 39.9 | 29 Oct 2027 | Gate 2 | Consents Approved |
| STOR Field 9 BESS | Inverkeithing GSP | Storage | 49.9 | 30 Jul 2029 | Not stated | Scoping |
Recent changes
- Drumfad Battery Storage SystemSouth Scotland, StorageStatus changed from Scoping to Consents Approved
- Drumfad Battery Storage SystemSouth Scotland, StorageConnection date moved from 31 Oct 2027 to 29 Oct 2027 (2 days earlier)
- Drumfad Battery Storage SystemSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Drumfad Battery Storage SystemSouth Scotland, StorageConnection point changed from Helensburgh 33kV Substation to Helensburgh 132/33kV
- STOR Field 9 BESSSouth Scotland, StorageAdded to the registerNew
- Drumfad Battery Storage SystemSouth Scotland, StorageCustomer changed from CAPBAL FAUNE LIMITED to EKU ENERGY FAUNE PROJECTS (UK) LIMITED
- Drumfad Battery Storage SystemSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?