EDF ENERGY (THERMAL GENERATION) LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|
Left the register since January 2021: Cottam (0 MW), West Burton A (0 MW).
Recent changes
- CottamEngland and Wales, Thermal (gas, biomass, waste)Left the register (0 MW)0 MW
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Left the register (900 MW connected − 900 MW from 1 Apr 2023)0 MW
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from West Burton 400kV to West Burton 400kV Substation)
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)1,075 MW no longer connected
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from −1,075 MW to −900 MW
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 1 Apr 2022 to 1 Apr 2023
- CottamEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Cottam 400kV to Cottam 400kV Substation)
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 0 MW to −1,075 MW
- West Burton AEngland and Wales, Thermal (gas, biomass, waste)Connection date set to 1 Apr 2022
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?