Eccles Energy Centre Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Eccles BESS | Eccles 400kV Substation | Storage | 500 | 12 Apr 2026 Past date −8 mo | Gate 2 | Under Construction/Commissioning |
Recent changes
- Eccles BESSSouth Scotland, StorageStatus changed from Scoping to Under Construction/Commissioning
- Eccles BESSSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Eccles BESSSouth Scotland, StorageConnection date moved from 4 Dec 2026 to 12 Apr 2026 (−8 months)−8 mo
- Eccles BESSSouth Scotland, StorageConnection date moved from 12 Apr 2026 to 4 Dec 2026 (+8 months)+8 mo
- Eccles BESSSouth Scotland, StorageCustomer changed from WEAVER POWER LIMITED to Eccles Energy Centre Limited
- Eccles BESSSouth Scotland, StorageConnection point changed from Eccles 132/33kV to Eccles 400kV Substation
- Eccles BESSSouth Scotland, StorageConnection point changed from Eccles 400/132/33kV to Eccles 132/33kV
- Eccles BESSSouth Scotland, StorageConnection point changed from Eccles 400kV Substation to Eccles 400/132/33kV
- Eccles BESSSouth Scotland, StorageTechnology changed from Reactive compensation to Storage
- Eccles BESSSouth Scotland, StorageCapacity changed from 200 MW to 500 MW
- Eccles BESSSouth Scotland, StorageConnection date moved from 31 Aug 2026 to 12 Apr 2026 (−5 months)−5 mo
- Eccles BESSSouth Scotland, StorageSubstation name updated in the register (from Eccles 400kV to Eccles 400kV Substation)
- Eccles BESSSouth Scotland, StorageTechnology changed from Storage, Reactive compensation to Reactive compensation
- Eccles BESSSouth Scotland, StorageCapacity changed from 0 MW to 200 MW
- Eccles BESSSouth Scotland, StorageConnection date moved from 12 Apr 2026 to 31 Aug 2026 (+5 months)+5 mo
- Eccles BESSSouth Scotland, StorageTechnology changed from Reactive compensation to Storage, Reactive compensation
- Eccles BESSSouth Scotland, StorageRenamed from Eccles 400kV Substation
- Eccles BESSSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?