EastCoastGridServices Ltd
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Branxton Energy Storage Facility | Branxton 400kV Substation | Storage | 750 | 13 May 2029 | Not stated | Scoping |
Recent changes
- Branxton Energy Storage FacilitySouth Scotland, StorageConnection point changed from Branxton 400/132kV to Branxton 400kV Substation
- Branxton Energy Storage FacilitySouth Scotland, StorageConnection date moved from 30 Dec 2027 to 13 May 2029 (+16 months)+16 mo
- Branxton Energy Storage FacilitySouth Scotland, StorageConnection point changed from Branxton 400kV Substation to Branxton 400/132kV
- Branxton Energy Storage FacilitySouth Scotland, StorageConnection point changed from Bowsheil 132kV Substation to Branxton 400kV Substation
- Branxton Energy Storage FacilitySouth Scotland, StorageConnection point changed from Branxton 400kV Substation to Bowsheil 132kV Substation
- Branxton Energy Storage FacilitySouth Scotland, StorageCapacity changed from 500 MW to 750 MW
- Branxton Energy Storage FacilitySouth Scotland, StorageCustomer changed from GRIDCODEPOWER LTD to EastCoastGridServices Ltd
- Branxton Energy Storage FacilitySouth Scotland, StorageCustomer changed from EastCoastGridServices Ltd to GRIDCODEPOWER LTD
- Branxton Energy Storage FacilitySouth Scotland, StorageSubstation name updated in the register (from Branxton 400kV to Branxton 400kV Substation)
- Branxton Energy Storage FacilitySouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?