CUMBERHEAD WEST WIND FARM LTD.
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Cumberhead West Wind Farm | Cumberhead 33kV | Onshore wind | 0 | Connected | Not stated | Built |
Recent changes
- Cumberhead West Wind FarmSouth Scotland, Onshore wind114 MW now connectedConnected
- Cumberhead West Wind FarmSouth Scotland, Onshore windGate marking removed (was Gate 2)
- Cumberhead West Wind FarmSouth Scotland, Onshore windConnection date moved from 31 Jul 2025 to 8 Dec 2025 (+4 months)+4 mo
- Cumberhead West Wind FarmSouth Scotland, Onshore windStatus changed from Awaiting Consents to Built
- Cumberhead West Wind FarmSouth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
- Cumberhead West Wind FarmSouth Scotland, Onshore windConnection date moved from 1 Nov 2024 to 31 Jul 2025 (+9 months)+9 mo
- Cumberhead West Wind FarmSouth Scotland, Onshore windConnection point changed from Cumberhead West GSP to Cumberhead 33kV
- Cumberhead West Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Cumberhead West to Cumberhead West GSP)
- Cumberhead West Wind FarmSouth Scotland, Onshore windCapacity changed from 100 MW to 114 MW
- Cumberhead West Wind FarmSouth Scotland, Onshore windConnection point changed from Cumberhead to Cumberhead West
- Cumberhead West Wind FarmSouth Scotland, Onshore windConnection date moved from 11 Jan 2024 to 1 Nov 2024 (+10 months)+10 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?