CRYSTAL RIG IV LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Crystal Rig IV Wind Farm | Crystal Rig 400kV substation | Onshore wind | 0 | Connected | Not stated | Built |
Recent changes
- Crystal Rig IV Wind FarmSouth Scotland, Onshore wind48.2 MW now connectedConnected
- Crystal Rig IV Wind FarmSouth Scotland, Onshore windGate marking removed (was Gate 2)
- Crystal Rig IV Wind FarmSouth Scotland, Onshore windStatus changed from Under Construction/Commissioning to Built
- Crystal Rig IV Wind FarmSouth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
- Crystal Rig IV Wind FarmSouth Scotland, Onshore windConnection date moved from 30 Jun 2024 to 13 Oct 2025 (+15 months)+15 mo
- Crystal Rig IV Wind FarmSouth Scotland, Onshore windConnection point changed from Crystal Rig 132/33kV to Crystal Rig 400kV substation
- Crystal Rig IV Wind FarmSouth Scotland, Onshore windConnection point changed from Crystal Rig 400/132/33kV to Crystal Rig 132/33kV
- Crystal Rig IV Wind FarmSouth Scotland, Onshore windConnection point changed from Crystal Rig 400/132kV Substation to Crystal Rig 400/132/33kV
- Crystal Rig IV Wind FarmSouth Scotland, Onshore windConnection date moved from 1 Apr 2022 to 30 Jun 2024 (+27 months)+27 mo
- Crystal Rig IV Wind FarmSouth Scotland, Onshore windConnection date moved from 4 Jan 2022 to 1 Apr 2022 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?