Central Bedfordshire Council
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Biggleswade BESS | Biggleswade 400kV Substation | Storage | 57 | 28 Sep 2029 −1 mo | Gate 1 | Scoping |
Recent changes
- Biggleswade BESSEngland and Wales, StorageConnection date moved from 31 Oct 2029 to 28 Sep 2029 (−1 month)−1 mo
- Biggleswade BESSEngland and Wales, StorageMarked as Gate 1
- Biggleswade BESSEngland and Wales, StorageSubstation name updated in the register (from Biggleswade GSP to Biggleswade 400kV Substation)
- Biggleswade BESSEngland and Wales, StorageSubstation name updated in the register (from Biggleswade 400kV to Biggleswade GSP)
- Biggleswade BESSEngland and Wales, StorageSubstation name updated in the register (from Biggleswade GSP to Biggleswade 400kV)
- Biggleswade BESSEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?