CAMBRIDGE POWER LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Fife Energy Centre | Fife Energy Centre 132kV substation | Storage | 100 | 31 Oct 2028 | Gate 1 | Scoping |
| Red House Farm - Friston 400kV 249MW connection | South Anglia Connection Node E 400kV Substation | Storage | 249 | 31 Oct 2034 | Not stated | Scoping |
Left the register since January 2021: Ridham Battery Storage (350 MW).
Recent changes
- Fife Energy CentreSouth Scotland, StorageMarked as Gate 1
- Fife Energy CentreSouth Scotland, StorageConnection date moved from 28 Apr 2028 to 31 Oct 2028 (+6 months)+6 mo
- Red House Farm - Friston 400kV 249MW connectionEngland and Wales, StorageConnection point changed from Friston 400kV Substation to South Anglia Connection Node E 400kV Substation
- Ridham Battery StorageEngland and Wales, StorageLeft the register (350 MW from 31 Oct 2031)350 MW
- Red House Farm - Friston 400kV 249MW connectionEngland and Wales, StorageAdded to the registerNew
- Ridham Battery StorageEngland and Wales, StorageConnection point changed from Kemsley 400/132kV Substation to Kemsley 400kV Substation
- Ridham Battery StorageEngland and Wales, StorageAdded to the registerNew
- Fife Energy CentreSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?