Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

BENBRACK WIND FARM LIMITED

Customer named in the TEC register

2projects in the register
42 MWstill to connect
0 MWof that with Gate 2 offers
72 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Lamford HillBenbrack Wind Farm 132/33kV SubstationStorage with solar or wind4231 Aug 2029Gate 1Scoping
Benbrack Wind FarmBenbrack Wind Farm 132/33kV SubstationOnshore wind0ConnectedNot statedBuilt

Recent changes

  • Lamford HillSouth Scotland, Storage with solar or windStage 1: Marked as Gate 1
  • Lamford HillSouth Scotland, Storage with solar or windStage 2: Marked as Gate 1
  • Benbrack Wind FarmSouth Scotland, Onshore wind72 MW now connectedConnected
  • Benbrack Wind FarmSouth Scotland, Onshore windStatus changed from Awaiting Consents to Built
  • Lamford HillSouth Scotland, Storage with solar or windRestructured from 1 stage (20 MW from 30 Oct 2026) to 2 stages (20 MW from 31 Aug 2029, 22 MW from 31 Oct 2036). First connection date +34 months+34 mo
  • Lamford HillSouth Scotland, Storage with solar or windCustomer changed from RWE RENEWABLES UK ONSHORE WIND LIMITED to Benbrack Wind Farm Limited
  • Lamford HillSouth Scotland, Storage with solar or windCustomer changed from Benbrack Wind Farm Limited to RWE RENEWABLES UK ONSHORE WIND LIMITED
  • Benbrack Wind FarmSouth Scotland, Onshore windConnection date moved from 30 May 2024 to 30 Jan 2025 (+8 months)+8 mo
  • Lamford HillSouth Scotland, Storage with solar or windCustomer changed from RWE RENEWABLES UK ONSHORE WIND LIMITED to Benbrack Wind Farm Limited
  • Benbrack Wind FarmSouth Scotland, Onshore windConnection point changed from Benbrack 33kV Substation to Benbrack Wind Farm 132/33kV Substation
  • Lamford HillSouth Scotland, Storage with solar or windSubstation name updated in the register (from Lamford Hill 132/33kV Substation to Lamford Hill 132kV/33kV Substation)
  • Lamford HillSouth Scotland, Storage with solar or windCustomer changed from RWE RENEWABLES UK DEVELOPMENTS LIMITED to RWE RENEWABLES UK ONSHORE WIND LIMITED
  • Lamford HillSouth Scotland, Storage with solar or windAdded to the registerNew
  • Benbrack Wind FarmSouth Scotland, Onshore windCustomer changed from RWE RENEWABLES UK DEVELOPMENTS LIMITED to Benbrack Wind Farm Limited
  • Benbrack Wind FarmSouth Scotland, Onshore windConnection date moved from 30 May 2023 to 30 May 2024 (+12 months)+12 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO