ALCEMI STORAGE DEVELOPMENTS 5 LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Alcemi Score 2 Battery Energy Storage Facility | Alcemi Score Battery 400kV Substation | Storage | 500 | 31 Mar 2031 +17 mo | Gate 1 | Scoping |
| Alcemi Score Battery Energy Storage Facility | ALCEMI SCORE BATTERY ENERGY STORAGE FACILITY 400KV SUBSTATION | Storage | 500 | 31 Mar 2031 +17 mo | Gate 1 | Scoping |
Recent changes
- Alcemi Score 2 Battery Energy Storage FacilityNorth Scotland, StorageConnection date moved from 31 Oct 2029 to 31 Mar 2031 (+17 months)+17 mo
- Alcemi Score Battery Energy Storage FacilityNorth Scotland, StorageConnection date moved from 31 Oct 2029 to 31 Mar 2031 (+17 months)+17 mo
- Alcemi Score Battery Energy Storage FacilityNorth Scotland, StorageConnection point changed from Alcemi Score Battery 400kV Substation to ALCEMI SCORE BATTERY ENERGY STORAGE FACILITY 400KV SUBSTATION
- Alcemi Score 2 Battery Energy Storage FacilityNorth Scotland, StorageMarked as Gate 1
- Alcemi Score Battery Energy Storage FacilityNorth Scotland, StorageMarked as Gate 1
- Alcemi Score Battery Energy Storage FacilityNorth Scotland, StorageCustomer changed from ALCEMI STORAGE DEVELOPMENTS LIMITED to ALCEMI STORAGE DEVELOPMENTS 5 LIMITED
- Alcemi Score 2 Battery Energy Storage FacilityNorth Scotland, StorageTransmission owner changed from SPT to SHET
- Alcemi Score 2 Battery Energy Storage FacilityNorth Scotland, StorageConnection point changed from Peterhead GSP to Alcemi Score Battery 400kV Substation
- Alcemi Score 2 Battery Energy Storage FacilityNorth Scotland, StorageTransmission owner changed from SHET to SPT
- Alcemi Score Battery Energy Storage FacilityNorth Scotland, StorageCustomer changed from ALCEMI STORAGE DEVELOPMENTS 5 LIMITED to ALCEMI STORAGE DEVELOPMENTS LIMITED
- Alcemi Score 2 Battery Energy Storage FacilityNorth Scotland, StorageSubstation name updated in the register (from Peterhead to Peterhead GSP)
- Alcemi Score 2 Battery Energy Storage FacilityNorth Scotland, StorageAdded to the registerNew
- Alcemi Score Battery Energy Storage FacilityNorth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose