Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue.

More analyses are on the way.

Delays and exits in the transmission queue since 2021

How often do connection dates move, and how many projects leave the queue? We’ve followed every project in NESO’s TEC register since January 2021 to find out. Developers and investors can use this page to judge how likely a connection date is to hold when they plan or value a project. Anyone working on connections reform can see whether projects leave the queue when their securities rise. The figures on this page update with each new register.

The registers behind this page

QueueWatch holds 148 of NESO’s TEC registers, from 29 January 2021 to 27 October 2026: one a month until October 2025 and twice a week since December 2025. We follow each project from register to register, through NESO’s changes of project ID and site name.

1. Connection dates: how often and how far they move

In 2025, 17% of projects had their connection date pushed back, by a median of 24 months, and a quarter of those by 36 months or more. In 2021, more dates were pushed back (46%), but by less (a median of 10 months). In no year did more than 4% move earlier. Of the 156 projects whose connection date was pushed back in 2026 so far, 67 got the later date with their Gate 2 offer.

17%pushed back in 2025
24 monthsthe median move

Connection dates pushed back and brought forward

Share of the projects we could compare

Pushed backBrought forward*2026 to 27 Oct

How far the pushed-back dates moved

Months

MedianMiddle half of the moves*2026 to 27 Oct
Connection dates moved by year: All technologies
YearProjects comparedPushed backBrought forwardUnchangedPushed back %Brought forward %Median months pushed backLower quartileUpper quartile
2021303139915545.93.010416
2022448111832924.81.81410.523
202363186554013.60.814.511.324.8
20241,1401843692016.13.2231236
20251,455250201,18517.21.4241236
2026 to 27 Oct1,723156341,5339.12.019.51233

What it means: when a connection date is pushed back, it’s usually by a year or more, and the further away a project’s connection date is, the more years there are in which that date can be pushed back. A plan or valuation built on a single connection date leaves that risk out.

How we measured it

For each year, we compare each project’s connection date at the start of the year with its date at the end (for 2026, on 27 October), so we see how far it moved overall, not each move in between. Only projects that still have MW to connect and a date at both points count. A date changes with a project’s Gate 2 offer when it changes in the register that first shows the offer.

2. Exits: how much of the queue leaves each year

The queue held 551 GW at the start of 2025, and 1.9% of it left during the year. The highest share since 2021 was 9.6%, in 2023, when most of what left was offshore wind. Battery storage was the largest part of what left in 2025, 5.5 GW of the 11.9 GW, and that year 24 battery projects left, against 6 in 2021.

1.9%of the queue left in 2025
24battery projects left in 2025
Exits byMWProjects

Capacity that left the queue

Still to connect when it left, by technology

StorageSolarOnshore windOffshore windThermalHybridOther*2026 to 27 Oct

Share of the queue that left

Share of the queue at the start of each year that left that year

*2026 to 27 Oct
Exits by year, in MW: All technologies
YearStorageSolarOnshore windOffshore windThermalHybridOtherAllQueue at the start of the yearShare that left
2021313.6150112.54,7803,262.5008,618.6104,598.18.1%
20225550478.52,000002,4945,077.5165,062.53.1%
2023306.9202.874.921,9001,39903,79027,673.6241,453.89.6%
20243,860.8817282.211,7651,749.94,392.42,40025,267.3432,020.44.8%
20255,481.1179464.23,0001001,97968111,884.3551,453.71.9%
2026 to 27 Oct900049.9008473,6005,396.9620,051.80.9%

What it means: only a small share of the queue leaves each year, so a project shouldn’t rely on others dropping out to get an earlier connection.

How we measured it

A project has left when it drops out of NESO’s register for good. One that comes back later, even under a new project number, hasn’t left. We date each exit to the first register the project is missing from. A project missing from the latest registers could still come back, so this year’s figures may fall as new registers come out. We only count projects with MW still to connect, and the register doesn’t say why a project left. NESO started numbering projects in September 2023. For earlier registers, we follow each project mainly by its name, site and customer, so a few renamed projects may show as exits in the early years.

3. Exits and the trigger date

Every project in the queue has a trigger date, usually three to four years before it’s due to connect. From that date, leaving costs more: the charge a project pays if it leaves (its cancellation charge) goes up, and so does the security it must put up to cover that charge. If projects were leaving to avoid that, many would leave just before their trigger date. Of the 175 projects that have left the queue since 2021, only 2 left in the six months before their trigger date. The rest left earlier (108) or later (65).

2 of 175left in the six months before their trigger date
65left after it

When projects left, against their trigger date

Each bar counts the projects that left in a six-month window before or after their trigger date. The orange bar is the last six months before it, when leaving still cost less.

The six months before the trigger dateTrigger date
Exits against the trigger date: All technologies
When they leftExitsMW still to connect
More than six months before10871,697
In the six months before2218.2
At or after6512,003
See all bandsSee less
Exits by months from the trigger date: All technologies
Months from the trigger dateExitsMW still to connect
More than 84 months before4037,249.3
79 to 84 months before54,633.4
73 to 78 months before199
67 to 72 months before3350
61 to 66 months before41,131.5
55 to 60 months before64,242.5
49 to 54 months before54,849.9
43 to 48 months before2900
37 to 42 months before64,099
31 to 36 months before85,790
25 to 30 months before82,529.9
19 to 24 months before5789
13 to 18 months before4852
7 to 12 months before114,181.5
1 to 6 months before2218.2
0 to 5 months after142,775.4
6 to 11 months after2145
12 to 17 months after123,507.9
18 to 23 months after11845.1
24 to 29 months after61,945.1
30 to 35 months after8318.7
36 months or more after122,465.8

What it means: so far, projects haven’t rushed to leave before their charge and security step up. CMP470, the commitment fee for batteries that Ofgem is minded to approve, aims to shrink the battery queue by setting a minimum security from the day a project accepts its Gate 2 offer.

How we measured it

The register doesn’t give trigger dates, so we estimate each one from the connection date in the last register that listed the project, using the rule in CUSC Section 15 (paragraph 2.2(a)). A project’s real trigger date can differ, for example if its connection date changed after the trigger date was set, or its agreement was signed less than three financial years before it connects. Until October 2025, NESO published one register a month, so for exits before then we know the month a project left but not the day.

What if your connection date is pushed back?

QueueQuant values your project across thousands of possible futures for its connection date and the market, and tells you whether to hold, cut MW, sell or walk away, and what would change that answer.

Price my projectSee worked examples

How to cite this page

You’re welcome to quote our figures, charts and findings with this credit:

QueueWatch by QueueQuant, “Delays and exits in the transmission queue since 2021”, queuequant.com/queuewatch/delays-and-exits/ (data to 27 October 2026). Contains data from NESO’s TEC register. Supported by National Energy SO Open Data.

Supported by National Energy SO Open Data. Registers from 29 January 2021 to 11 August 2026 are copies NESO released to QueueQuant on 19 October 2026 under the Environmental Information Regulations 2004 (request FOI/26/226). Later registers are QueueWatch’s own downloads from NESO’s Data Portal.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO