Transmission / Projects / England and Wales

Bryn Rhudd Energy Park

BRYN RHUDD ENERGY PARK LIMITED at Pont Abraham GSP

Connection date
31 Oct 2028
Gate
Not stated
Status
Scoping
Technology
Onshore wind
Total capacity
159 MW
Connected now
0 MW
Still to connect
159 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Embedded
Region
England and Wales
Project number
PRO-001918
In the register since
November 2023

Change history

Every change to this project across 150 registers from 29 Jan 2021 to 3 Nov 2026.

  • 3 Nov 2026 register
    Renamed from Bryn Glas Energy Park
  • 7 Aug 2026 register
    Customer changed from Bryn Glas Energy Park Limited to BRYN RHUDD ENERGY PARK LIMITED
  • 28 Nov 2023 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO