QueueQuant Research · Selling a grid connection

Sell now, or wait for the connection offer?

Your 50 MW battery project holds a grid connection agreement for July 2030. Under the connections reform, the network operator is due to send you a new connection offer (your Gate 2 offer) within the year. You expect that offer to give a connection date of July 2028, July 2030 or July 2033, with chances of 30%, 50% and 20%. You put the chance that the new connection offer arrives within 6 months at 50%, and within the year at 75%. If no new connection offer comes this year, your current agreement carries on. Keeping the project costs you £50,000 a quarter.

Your questions

  1. What is the project worth if I sell it now?
  2. What is it worth if I wait for the new connection offer and sell then?
  3. Should I sell now or wait? And if I wait, how long before I sell without the new connection offer?

To answer your questions, QueueQuant’s stochastic optimisation engine plays out 4,000 possible futures for the project and works out what buyers would bid for it, today and once the new connection offer arrives.

What buyers would bid, as the QueueQuant engine calculates it
Today
£3.41m
before the new connection offer
If it connects in 2028
£5.12m
30% chance
If it connects in 2030
£4.09m
50% chance
If it connects in 2033
£2.82m
20% chance
If no new connection offer this year
£4.45m
25% chance; the bid at 12 months

Today’s bid allows for the chance of a 2033 date, because buyers don’t yet know what the new connection offer will say. The next three are the bids for each connection date if the new connection offer arrives in 3 months. If no new connection offer comes this year, your agreement keeps its July 2030 date with no risk of 2033, so the last bid is what buyers would pay for the project a year from now. All five bids are calculated in Step 3 below, which also shows the bids if the new connection offer arrives later, in 6, 9 or 12 months.

What would you do?

Pick one, then compare it with the answer below.

50%

Buyers put it at 50%. Move the slider to your own view and the answer will update.

Waiting would win if you put the chance below 22% or above 71%.

Sell now

Selling today, you’d receive £3.306m after costs. Waiting is worth £3.275m to you, so selling comes out £31k ahead.

Lowest bid to accept: £3.38m

Below this, you’re better off waiting.

If you wait anyway: Sell in 3 months if the new connection offer hasn’t come.

Based on questions clients bring to QueueQuant. The project is hypothetical, with its market figures taken from published sources; every result is calculated by the QueueQuant engine.

The scenario

What you (the seller) know today

Until the new connection offer arrives, nobody knows which connection date it will bring. Even after it arrives, much stays uncertain: the connection date can still slip (see how often dates move on QueueWatch), and the curtailment, the cost of the connection works and battery revenues aren’t known until nearer the build. A buyer bidding today has to allow for all of this. If you wait, you carry the risk until you sell.

Waiting lets you sell once the new connection offer has set the connection date, at a higher price if it brings the date forward to 2028. But waiting costs you more than it costs a buyer. Your cost of money (WACC) is 12% a year in real terms, against buyers’ 8%, so money now is worth more to you than to them. And a larger buyer can keep the project for about £40,000 a quarter, against your £50,000.

Already holding your Gate 2 offer? Our research on a Gate 2 offer and the commitment fee works through that position.

  • The project
    A 50 MW battery with planning consent for up to four hours of storage (200 MWh), and a grid connection agreement for July 2030.
  • The new connection offer
    You expect it to give a connection date of July 2028 (30% chance), July 2030 (50%) or July 2033 (20%).
  • When it arrives
    You put the chance it has arrived at 20% within 3 months, 50% within 6, 65% within 9 and 75% within 12.
  • If it doesn’t come
    Your current agreement carries on, with its July 2030 date, which can still slip.
  • Keeping the project
    Costs you £50,000 a quarter. It would cost a larger buyer about £40,000 a quarter.
  • Walking away
    Costs £150,000, the network’s cancellation charge of £3,000 per MW. This scenario has no commitment fee or deposit.
  • Selling
    Advisers’ fees of 1.5% of the price plus £50,000 of legal costs, and in any quarter a 1 in 20 chance that no buyer turns up.
  • Cost of money (WACC)
    Yours is 12% a year in real terms. Buyers’ is 8%.

How the answers are worked out

QueueQuant’s engine answers your questions in five steps. Steps 1 to 3 work out what buyers would pay for the project, whatever date the new connection offer brings. Steps 4 and 5 then compare selling now with waiting, using your own view, as the seller, of the chances and your costs.

Step 1 of 5

Map how the new connection offer could turn out

This step maps when the new connection offer could arrive over the coming year, and which connection date it could bring. Whether to sell now or wait depends on these chances.

The year is split into quarters. In each quarter, the new connection offer either arrives, with one of the three connection dates, or it doesn’t. The engine prices every box where the outcome is known. Each “New connection offer” box holds three cases, one for each connection date. With the “No new connection offer” box at 12 months, that makes 13 cases. The other boxes, where you’re still waiting, are worked out from these in Step 3.

Play out the coming year once to follow one path through the map, or 1,000 times to see the chances at work.

Uses your chance of a new connection offer within 6 months: 50%. You can change it at the top of the page or in Step 4.

Scroll sideways to see the whole year.

Percentages are chances from today. Each new connection offer brings 2028, 2030 or 2033, with chances of 30%, 50% and 20%.

What to notice. In the scenario, there’s a 25% chance that no new connection offer comes this year. Then your current agreement carries on, with its July 2030 date. The last of the five bids at the top of the page is for that case.

Step 2 of 5

How the engine prices one case

This step shows how the engine works out what a buyer would bid in one case. Every bid on this page comes from bids worked out this way.

Take one case from the map: the new connection offer arrives in 3 months, with a 2030 connection date. What would a buyer bid for the project then? Nothing is built yet. So the buyer is bidding for the right to build a battery at this connection, and for the choices that come with it. The engine values those choices by planning the project, as a buyer would, across 4,000 possible futures.

What happens after the sale, and when things become known

The sale

When the new connection offer arrives
Known
The connection date in the new connection offer: 2030.
Decided
How many of the 50 MW to keep (here, all 50). Any not kept are handed back to the network.
Money
The bid. The buyer takes over the agreement and the deposit lodged with the network.

Holding

Until the build decision
Money
Connection charge payments as they fall due, deposit top-ups and bank fees, land and advisers.

The build decision

About 18 months before the expected connection date
Known
Whether the connection date has slipped, the network’s curtailment estimate, the cost of the connection works still to pay and the market outlook.
Decided
Build, 2 or 4 hoursDrop it
Money
The battery is paid for in stages from the order. Dropping the project pays the cancellation charge from the deposit.

Connection

2030, or later if it slips
Known
A late slip in the connection date, which can leave the battery built but idle, a curtailment surprise, how strong the market turns out, and the Capacity Market price and whether the project wins an agreement.
Decided
Nothing. All of this arrives after the battery is ordered.

Operation

To the end of the battery’s life
Money
Trading revenues and Capacity Market payments, less running costs, network charges, a top-up to keep the battery’s capacity as it ages, and decommissioning.

The engine makes one build decision for each way the connection could go. That decision holds in every market future that follows, because when the buyer decides, the market’s ups and downs are still to come.

The 4,000 futures

The engine plays out 100 ways the connection could go, each bringing different news by the build decision. Each is played against the same 40 market futures, from the weakest market to the strongest. In the chart, each row is one connection outcome and each cell one future. The colour shows what the project is worth to the buyer there, in money at the date of the bid.

Where the engine drops the project, the loss is the same in every market future, so the whole row is one colour. Click a row, or step through them, to see what the buyer knew there and why the engine chose as it did.

Weakest market40 market futuresStrongest market
Rows sorted by value, highest at the top.
−£14.82m£0£40m
BuildDrop

The thin band on the left of each row shows the engine’s choice for that outcome: teal for build, brown for drop.

row 1

From 4,000 results to one bid

Each row ends with one value. It’s 0.75 of the average over the row’s 40 market futures, plus 0.25 of the average of its 2 worst, the worst 1 in 20. At each row, the engine makes the choice that gives the highest value. The 0.25 is the buyers’ weight on the downside, which reflects their risk appetite. Move it below to see how this bid changes. Your own weight, as the seller, comes in Step 4.

The engine then combines the 100 rows the same way: 0.75 of their average, plus 0.25 of the average of the 5 worst. The result is the bid: the most a buyer wanting 8% a year, and weighing the downside this way, would pay.

Each dot is one connection outcome: teal where the buyer builds, brown where it drops. The 5 worst, the worst 1 in 20, are ringed in amber. The larger, outlined dot is the outcome whose details are open above, under “Step through the rows”. Click any dot to open its details in that panel.

Average of the outcomes
£5.64m
Average of the 5 worst
−£0.57m
The bid
£4.09m ±0.65
0.25

Buyers in this scenario use 0.25. Moving it changes this case only.

What to notice. At the buyers’ weight of 0.25, the bid sits well below the average of the outcomes, because the worst outcomes count for more. At that weight, switching to “Build whatever happens” lowers the bid. The right to drop the project where the news is bad is worth money to a buyer.

That’s one case. The engine prices all 13 cases this way, on the same futures. So the differences between the cases come from the new connection offer, not from luck.

Step 3 of 5

Price every case the same way

This step prices all 13 cases the way Step 2 priced one. They’re the bids you could sell at later: once the new connection offer has come, or at the end of the year without one.

Today’s bid, and the bids while no new connection offer has come, are then built from these.

What buyers would bid in each case

By when the new connection offer arrives and the connection date it brings. The ± figure is each bid’s 95% band (see Step 2).

The shaded cell is the case in Step 2.

What to notice. The connection date makes the biggest difference. If the new connection offer arrives in 3 months, buyers would bid £5.12m for a 2028 date but £2.82m for 2033. For the same connection date, the bids rise each quarter. The project is a quarter nearer, and there’s one less quarter of holding costs to pay. The 2028 bids rise faster still: a later sale means a later battery order, so the battery spends less time built but idle if the connection slips.

Step 4 of 5

Compare selling now with waiting

This step answers the question: sell now, or wait? It uses the buyers’ bids from Step 3, and your own view, as the seller, of the chances and your costs.

The tree below has the same boxes as the map in Step 1, one for each point in the year. At each box, the engine compares two things. One is selling at the buyers’ bid, less the selling costs of 1.5% of the price plus £50,000. The other is paying for another quarter and waiting. The selling figure allows for the 1 in 20 chance that no buyer turns up and you have to try again next quarter, with the same 1 in 20 chance. The engine starts at the end of the year, where you must sell or walk away, and works back to today.

Move the sliders to your own view, and click any box to see the comparison behind its answer.

50%

Buyers assume 50%.

12%

A year, in real terms. Buyers’ is 8%.

£50k

A quarter.

0.25

At 0, only the average counts. At 1, only the worst 1 in 20 outcomes count.

Today
Sell now

Selling today, you’d receive £3.306m after costs. Waiting is worth £3.275m to you, so selling comes out £31k ahead.

Lowest bid to accept
£3.38m

Below this, you’re better off waiting. After the selling costs, a lower bid would leave you less than the £3.275m waiting is worth to you. Buyers would bid £3.41m.

Waiting, on average
£3.46m
Worst 1 in 20, on average
£2.70m
Chance of ending below a sale today
4%

If you wait, about 96 times in 100 you end up with more than the £3.306m you’d get by selling today, and about 4 times in 100 with less. But when waiting goes wrong, it goes badly wrong: the worst 1 in 20 outcomes leave you with about £2.70m on average. Your weight on the downside (0.25) makes those outcomes count for more, which brings waiting’s worth down to £3.275m, just below the £3.306m from selling today.

If you wait anyway
Sell in 3 months if the new connection offer hasn’t come.

Each box shows the best thing to do there, and what buyers would bid. “Hold” means keeping the project another quarter. “Depends” means the answer differs by connection date. Click a box to see the comparison behind it. Scroll sideways to see the whole year.

What to notice. In the scenario, waiting doesn’t mean waiting all year. The best plan of waiting gives the new connection offer 3 months to arrive. If it hasn’t come by then, you sell. Click that box in the tree to see why.

Step 5 of 5

Find the switch points

This step finds the switch points: the value of each assumption at which the answer changes between selling now and waiting. They show how sure you need to be about each assumption before you act on the answer.

None of these assumptions is certain. So a study for your project gives each switch point in plain words, and you judge which side of it your own project is on. With the settings above:

    What to notice. Look for the switch point closest to your own setting. The closer it is, the more the answer depends on getting that assumption right.

    What the scenario shows

    The answer depends on where you differ from buyers

    Today’s bid already allows for the new connection offer

    Buyers bid today for the chance of a good new connection offer, at the odds they see. If you saw the chances and costs exactly as they do, selling and waiting would come out about level, with waiting £34k ahead. This seller’s money costs 12% a year, against buyers’ 8%. Keeping the project costs £50,000 a quarter, against £40,000. So selling wins, narrowly.

    Your edge is what you know

    Waiting wins when you differ from buyers in a way that counts. Your letters from the network may tell you more than buyers know about when the new connection offer will come. Or money may cost you less than it costs them. Step 5 shows how far each would have to move.

    For your own project

    What we’ll work out for your project

    A study for your project uses your own connection offer and letters, the network’s curtailment assessment, your costs and a market forecast. It prices the project for two kinds of buyer, a typical one and a cautious one. So you can see how much the answer depends on who bids.

    The lowest bid to accept now

    The bid below which you’re better off waiting, allowing for the costs of the sale.

    A fair fixed price with an uplift

    If you sell now, with an extra payment (an uplift) should a good new connection offer arrive: the fixed price that’s fair to both sides.

    What waiting is likely to be worth

    The spread of what you could end up with if you wait, with its downside and the chance of ending below a sale today.

    How long to wait before giving up

    The point after which selling without the new connection offer beats waiting any longer for it.

    We will give you a report where every assumption is listed with its source and the switch points are given in plain words. One re-run after your comments is included. The report is decision support. It isn’t investment advice or a formal valuation.

    How to cite this page

    You’re welcome to quote our figures, charts and findings with this credit:

    QueueQuant Research, “Sell now, or wait for your Gate 2 offer?”, queuequant.com/research/selling-a-grid-connection/ (October 2026).